Filling 5,000 molds at 30 lb per mold requires 150,000 lb (75 tons) of concrete, which equals roughly 37.5 to 38.5 cubic yards (assuming standard 145–150 lb/cu ft concrete). At 20 in × 30 in (600 sq in = 4.17 sq ft), each 30 lb pour creates a thin panel roughly 0.58 inches thick.
Because these are thin, high-repetition castings, the bottleneck is indexing and metering, not raw pumping power. You should not pump directly out of a pressurized hose into each mold—moving a heavy, pressurized hose 5,000 times causes operator fatigue, messy overfills, and air entrapment in a ~0.6-inch-thick mold.
The Best Setup: Continuous Feed into a Stationary Gated Dispenser (Carousel or Conveyor Line)
Rather than moving the concrete to 5,000 molds, keep the discharge point stationary and move the molds underneath it on a roller conveyor or rotary indexing table.
* Continuous Mixing & Delivery:
* Feed a continuous volumetric mixer (or pump from a ready-mix truck/batch mixer) at a steady rate—for example, 6 lb/second fills one 30 lb mold every 5 seconds, completing all 5,000 molds in roughly 7 hours of continuous runtime (not counting cure/demold cycling).
* Discharge the continuous stream into an elevated agitator surge hopper (holding ~500–1,000 lb / 3.5–7 cu ft) mounted directly above the conveyor line. Keeping a small, agitated buffer absorbs flow fluctuations so the mixer never has to stop and start.
* Volumetric or Timed Metering Gate:
* Fit the bottom of the surge hopper with a pneumatic knife gate (slide gate) or a clamshell/sector gate sized to span across the 20-inch width of the mold (a 16–18 inch wide rectangular chute distributes the concrete across the mold width so it doesn't have to flow far in a thin 0.58-inch cavity).
* Trigger the gate via a limit switch or timer: at 6 lb/sec, opening the gate for exactly 5 seconds drops a 30 lb ribbon across the mold as it passes underneath, or while it pauses briefly on an indexing roller.
* Inline Vibration:
* Place a vibrating roller section or vibrating table plate immediately downstream of the fill chute. Because a 30 lb pour in a 20" × 30" mold is less than 5/8 inch thick, self-consolidating concrete (SCC) or a 3-second high-frequency vibration pass is critical to level the corners and expel trapped air bubbles.
Alternative Setup: Moving Gantry Hopper (If Molds Must Stay Stationary)
If you are laying all 5,000 molds out on a warehouse floor or racking system and cannot convey them:
* Mount a wheeled gantry bridge or overhead crane hopper (holding 1,000–1,500 lb) with a bottom clamshell or guillotine gate that straddles the rows of molds.
* Refill the traveling hopper from your concrete pump every 35–50 molds, and roll it down the row opening and closing the gate over each mold. This eliminates dragging a pressurized concrete hose across 5,000 forms while still giving clean, drip-free shutoffs.
Mix Design Tip for 0.58-Inch-Thick Castings
With a 20" × 30" footprint at 30 lb, maximum aggregate size should be 3/8 inch (pea gravel) or smaller—ideally a self-consolidating mortar or micro-concrete mix with a polycarboxylate superplasticizer. Standard 3/4-inch stone will bridge across a 0.58-inch thickness, jam a bottom-dump gate, and leave surface voids.